Progress

Manufacturing

Pacific Precision is able to make the output shafts; unfortunately they will not be done until late next week. We also confirmed that the robot frames will be ready to be picked up from Central Powder Coating at the end of business day Thursday.  We continued progress on machining the bumper mounting pins, and will begin on the kicker piston bearing cones once the bumper mounting parts are complete.

Design

The control board CAD is being revised and we purchased all of the components for the boards.

Other News

We secured a local embroidering shop to make the team numbers on the bumpers.

We have contacted Motion Industries for a quote for all the ball bearings, and are currently awaiting word back.